gsd_state_version, milestone, milestone_name, status, stopped_at, last_updated, last_activity, progress
gsd_state_version milestone milestone_name status stopped_at last_updated last_activity progress
1.0 v2.2 v2.2 Report Branding & User Directory defining-requirements Defining requirements 2026-04-08T00:00:00Z 2026-04-08 — Milestone v2.2 started
total_phases completed_phases total_plans completed_plans
0 0 0 0

Project State

Project Reference

See: .planning/PROJECT.md (updated 2026-04-08)

Core value: Administrators can audit and manage SharePoint/Teams permissions and storage across multiple client tenants from a single, reliable desktop application. Current focus: v2.2 Report Branding & User Directory — HTML report logos, user directory browse mode

Current Position

Phase: Not started (defining requirements) Plan: — Status: Defining requirements Last activity: 2026-04-08 — Milestone v2.2 started

v2.2 Progress: [░░░░░░░░░░] 0%

Accumulated Context

Decisions

Decisions are logged in PROJECT.md Key Decisions table.

v1.1 architectural notes:

  • Global site selection (Phase 6) changes the toolbar; all tabs must bind to a shared GlobalSiteSelectionViewModel or equivalent. Use WeakReferenceMessenger for cross-tab site-changed notifications, consistent with v1.0 messenger usage.
  • Per-tab override (SITE-02) means each FeatureViewModelBase subclass stores a nullable local site override; null means "use global".
  • Storage Visualization (Phase 9) requires a WPF charting NuGet (LiveCharts2 recommended — actively maintained, WPF-native, self-contained friendly). Wire chart data binding to the existing storage scan result model.
  • Self-contained EXE constraint: charting library must not require runtime DLLs outside the publish output.

Pending Todos

None.

Blockers/Concerns

None.

Session Continuity

Last session: 2026-04-08 Stopped at: Milestone v2.2 started — defining requirements Resume file: None