chore: complete v1.0 milestone
Archive 5 phases (36 plans) to milestones/v1.0-phases/.
Archive roadmap, requirements, and audit to milestones/.
Evolve PROJECT.md with shipped state and validated requirements.
Collapse ROADMAP.md to one-line milestone summary.

Co-Authored-By: Claude Opus 4.6 (1M context) <noreply@anthropic.com>
2026-04-07 09:15:14 +02:00

29 lines
1.1 KiB
Markdown

# Roadmap: SharePoint Toolbox v2
## Milestones
-**v1.0 MVP** — Phases 1-5 (shipped 2026-04-07) — [archive](milestones/v1.0-ROADMAP.md)
## Phases
<details>
<summary>✅ v1.0 MVP (Phases 1-5) — SHIPPED 2026-04-07</summary>
- [x] Phase 1: Foundation (8/8 plans) — completed 2026-04-02
- [x] Phase 2: Permissions (7/7 plans) — completed 2026-04-02
- [x] Phase 3: Storage and File Operations (8/8 plans) — completed 2026-04-02
- [x] Phase 4: Bulk Operations and Provisioning (10/10 plans) — completed 2026-04-03
- [x] Phase 5: Distribution and Hardening (3/3 plans) — completed 2026-04-03
</details>
## Progress
| Phase | Milestone | Plans Complete | Status | Completed |
|-------|-----------|----------------|--------|-----------|
| 1. Foundation | v1.0 | 8/8 | Complete | 2026-04-02 |
| 2. Permissions | v1.0 | 7/7 | Complete | 2026-04-02 |
| 3. Storage and File Operations | v1.0 | 8/8 | Complete | 2026-04-02 |
| 4. Bulk Operations and Provisioning | v1.0 | 10/10 | Complete | 2026-04-03 |
| 5. Distribution and Hardening | v1.0 | 3/3 | Complete | 2026-04-03 |