Files
ImpTune/.planning/STATE.md
T
kawa bcd12a36c0 docs(10-02): clear BLOCKER-01 and resume plan at Task 2 after RTVAL-01 PASS
- STATE.md: status in-progress, stopped_at Task 2, BLOCKER-01 cleared
- ROADMAP.md: phase 10 plan progress recalculated
2026-04-13 14:11:39 +02:00

5.4 KiB

gsd_state_version, milestone, milestone_name, status, stopped_at, last_updated, last_activity, progress
gsd_state_version milestone milestone_name status stopped_at last_updated last_activity progress
1.0 v1.1 Hardening & Validation in-progress — plan 10-02 resumed; RTVAL-01 PASS on re-test against fixed build; paused at Task 2 (RTVAL-02 on-device install under SYSTEM) 10-02-live-intune-runtime-validation-PLAN.md — Task 2 (RTVAL-02) human-action checkpoint awaiting technician on-device install evidence 2026-04-13T00:00:00.000Z 2026-04-13 — RTVAL-01 re-tested PASS against fixed .intunewin build (commit 00b709d); ISSUE-01 resolved; plan 10-02 paused at Task 2
total_phases completed_phases total_plans completed_plans
4 1 4 4

Project State

Project Reference

See: .planning/PROJECT.md (updated 2026-04-13 after v1.0 milestone)

Core value: Generate a complete, working printer deployment package (script + drivers + icon) in minutes instead of manually scripting each printer setup. Current focus: v1.1 Hardening & Validation — Phase 8 (Nyquist Validation Track)

Current Position

Milestone: v1.1 Hardening & Validation Phase: 10 — Real-World Runtime Validation Plan: 02 in progress — Task 1 PASS (RTVAL-01); paused at Task 2 (RTVAL-02) human-action checkpoint Status: in-progress — RTVAL-01 re-tested PASS against fixed .intunewin build (commit 00b709d); awaiting on-device install evidence for RTVAL-02 Decision: Resume plan 10-02 after HMAC scope + Detection.xml generator fixes landed (commits 74535ea, 7716246); ISSUE-01 resolved Last activity: 2026-04-13 — RTVAL-01 PASS recorded (commit cf3b86a); plan 10-02 paused at Task 2 checkpoint

Milestone History

  • v1.0 — ImpTune MVP (shipped 2026-04-13) — see MILESTONES.md

Accumulated Context

v1.1 Phase Structure

  • Phase 8: Nyquist Validation Track (NYQ-01..03) — parallelizable audit track
  • Phase 9: UX Tech Debt Closure (UX-01..03) — must land before rollout
  • Phase 10: Real-World Runtime Validation (RTVAL-01..05) — must pass before rollout
  • Phase 11: Real-World Rollout & Feedback (RWR-01..04) — depends on Phases 9 + 10

Open Concerns (now owned by v1.1 phases)

  • Real-world Intune tenant .intunewin acceptance → Phase 10 (RTVAL-01)
  • pnputil + $PSScriptRoot under SYSTEM → Phase 10 (RTVAL-02..04)
  • Driver dropdown refresh after upload → Phase 9 (UX-01)
  • PRNT-03 Alpine.js port auto-derivation live verification → Phase 9 (UX-02)
  • Individual script download links on printer detail page → Phase 9 (UX-03)
  • Nyquist-compliant VALIDATION.md across v1.0 phases → Phase 8 (NYQ-01..03)

Decisions

  • Phase ordering: RTVAL before RWR (cannot deploy unvalidated runtime); UX before RWR (deployed build must be polished); NYQ parallel to all (pure audit, no code dependency) — placed first so v1.0 validation evidence is fresh before runtime work begins.
  • RTVAL grouping: RTVAL-01..05 combined into single Phase 10 because they share setup (same tenant, same test endpoint, same RUNTIME-VALIDATION.md report).
  • NYQ as dedicated phase: Kept standalone (not absorbed) because it audits all 7 v1.0 phases and its evidence feeds defect triage into Phases 9/10.

Full decision log in PROJECT.md Key Decisions table. Milestone v1.0 decisions archived in milestones/v1.0-ROADMAP.md.

  • [Phase 09-ux-tech-debt-closure]: 09-03: .ps1 routes added as aliases (not renames) to preserve backward compatibility
  • [Phase 09-ux-tech-debt-closure]: 09-03: Shared _*_response() helper pattern used for route aliases
  • [Phase 09]: Sentinel field (caller=printer_form) for OOB branching: chosen over HX-Target header for clarity and testability
  • [Phase 09]: HTMX OOB template includes primary fragment + OOB select sibling in driver_upload_with_oob.html
  • [Phase 09-ux-tech-debt-closure]: 09-02: /printers route used for e2e test (full-page with Alpine.js) — no new /printers/new route needed
  • [Phase 09-ux-tech-debt-closure]: 09-02: conftest.py adapted — imptune.config uses string paths, init_db() takes no args
  • [Phase 10-real-world-runtime-validation]: 10-01: Package under test is Ricoh PCL6 Universal Print (Copieur_2eme.intunewin), ImpTune commit 1c3f458, committed to evidence/ for traceability
  • [Phase 10-real-world-runtime-validation]: 10-01: Commit SHA locked before runtime testing — all RTVAL results reference this exact build
  • [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-01 FAIL — Stop plan 10-02; surface .intunewin structure defect as gap; use /gsd:debug on generator or /gsd:plan-phase 10 --gaps before retesting
  • [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-01 PASS on re-test (2026-04-13) — ISSUE-01 resolved by commits 74535ea (HMAC over IV+ciphertext) and 7716246 (Detection.xml alignment with IntuneWinAppUtil.exe reference format); plan resumed at Task 2

Active Blockers

None. BLOCKER-01 resolved 2026-04-13 via commits 74535ea (HMAC over IV+ciphertext) and 7716246 (Detection.xml aligned with IntuneWinAppUtil.exe reference format); RTVAL-01 re-tested PASS on fixed build.

Pending Todos

  • Run /gsd:plan-phase 8 to draft plans for Nyquist Validation Track
  • Schedule real Intune tenant + test endpoint access for Phase 10
  • Identify target MSP environment for Phase 11 rollout

Session Continuity

Last session: 2026-04-13T00:00:00.000Z Stopped at: 10-02-live-intune-runtime-validation — Task 2 (RTVAL-02) human-action checkpoint; awaiting on-device install evidence Resume file: .planning/phases/10-real-world-runtime-validation/10-02-live-intune-runtime-validation-PLAN.md