Files
Sharepoint-Toolbox/.planning/STATE.md
Dev dd2f179c2d docs(01-03): complete persistence layer plan — ProfileService + SettingsService
- SUMMARY.md: 7 files, 18 tests, write-then-replace pattern documented
- STATE.md: plan 03 complete, progress 38%, decisions recorded
- ROADMAP.md: phase 1 progress updated (3/8 plans done)
- REQUIREMENTS.md: FOUND-02, FOUND-10, FOUND-12 marked complete
2026-04-02 12:13:35 +02:00

3.9 KiB

gsd_state_version, milestone, milestone_name, status, stopped_at, last_updated, last_activity, progress
gsd_state_version milestone milestone_name status stopped_at last_updated last_activity progress
1.0 v1.0 milestone planning Completed 01-foundation-03-PLAN.md 2026-04-02T10:13:20.259Z 2026-04-02 — Roadmap created, requirements mapped, all 42 v1 requirements assigned to phases
total_phases completed_phases total_plans completed_plans percent
5 0 8 3 13

Project State

Project Reference

See: .planning/PROJECT.md (updated 2026-04-02)

Core value: Administrators can audit and manage SharePoint/Teams permissions and storage across multiple client tenants from a single, reliable desktop application. Current focus: Phase 1 — Foundation

Current Position

Phase: 1 of 5 (Foundation) Plan: 0 of ? in current phase Status: Ready to plan Last activity: 2026-04-02 — Roadmap created, requirements mapped, all 42 v1 requirements assigned to phases

Progress: [█░░░░░░░░░] 13%

Performance Metrics

Velocity:

  • Total plans completed: 0
  • Average duration: —
  • Total execution time: 0 hours

By Phase:

Phase Plans Total Avg/Plan
- - - -

Recent Trend:

  • Last 5 plans: —
  • Trend: —

Updated after each plan completion | Phase 01-foundation P01 | 4 | 2 tasks | 14 files | | Phase 01-foundation P02 | 1 | 2 tasks | 7 files | | Phase 01-foundation P03 | 8 | 2 tasks | 7 files |

Accumulated Context

Decisions

Decisions are logged in PROJECT.md Key Decisions table. Recent decisions affecting current work:

  • Foundation: Use PnP.Framework 1.18.0 (not PnP.Core SDK) — PnP Provisioning Engine lives only in PnP.Framework
  • Foundation: Use MsalCacheHelper for per-tenant token cache serialization — scope IPublicClientApplication per ClientId
  • Foundation: Never set PublishTrimmed=true — PnP.Framework and MSAL use reflection; accept ~150-200 MB EXE
  • Foundation: Establish AsyncRelayCommand + IProgress + CancellationToken patterns before any feature work — retrofitting is the most expensive WPF refactor
  • [Phase 01-foundation]: Upgraded MSAL from 4.83.1 to 4.83.3 — Extensions.Msal 4.83.3 requires MSAL >= 4.83.3; minor patch with no behavioral difference
  • [Phase 01-foundation]: Test project targets net10.0-windows with UseWPF=true — required to reference WPF main project; net10.0 is framework-incompatible
  • [Phase 01-foundation]: Solution uses .slnx format (new .NET 10 XML solution) — dotnet new sln creates .slnx by default in .NET 10 SDK
  • [Phase 01-foundation]: TenantProfile is a plain mutable class (not record) — System.Text.Json requires settable properties; field names Name/TenantUrl/ClientId match JSON schema exactly
  • [Phase 01-foundation]: SharePointPaginationHelper uses [EnumeratorCancellation] on ct — required for correct WithCancellation() forwarding in async iterators
  • [Phase 01-foundation]: Explicit System.IO using required in WPF project — WPF temp build project does not include System.IO in implicit usings; all persistence classes need explicit import
  • [Phase 01-foundation]: SettingsService validates only 'en' and 'fr' language codes — throws ArgumentException for unsupported codes
  • [Phase 01-foundation]: LoadAsync on corrupt JSON throws InvalidDataException (not silent empty) — explicit failure protects against silent data loss

Pending Todos

None yet.

Blockers/Concerns

  • Phase 3 planning: Duplicate detection at scale (100k+ files) — Graph API hash enumeration limits and client-side SHA256 approach need targeted research before planning
  • Phase 4 planning: PnP Provisioning Engine behavior for Teams-connected modern sites — edge cases need validation spike before planning
  • Phase 5: User access export (v2 requirement UACC-01/02) depends on Phase 2 PermissionsService — confirm scope before Phase 5 planning

Session Continuity

Last session: 2026-04-02T10:13:20.255Z Stopped at: Completed 01-foundation-03-PLAN.md Resume file: None