docs(01-03): complete persistence layer plan — ProfileService + SettingsService

- SUMMARY.md: 7 files, 18 tests, write-then-replace pattern documented
- STATE.md: plan 03 complete, progress 38%, decisions recorded
- ROADMAP.md: phase 1 progress updated (3/8 plans done)
- REQUIREMENTS.md: FOUND-02, FOUND-10, FOUND-12 marked complete
This commit is contained in:
Dev
2026-04-02 12:13:35 +02:00
parent ac3fa5c8eb
commit dd2f179c2d
4 changed files with 158 additions and 12 deletions

View File

@@ -104,7 +104,7 @@ Phases execute in numeric order: 1 → 2 → 3 → 4 → 5
| Phase | Plans Complete | Status | Completed |
|-------|----------------|--------|-----------|
| 1. Foundation | 2/8 | In Progress| |
| 1. Foundation | 3/8 | In Progress| |
| 2. Permissions | 0/? | Not started | - |
| 3. Storage and File Operations | 0/? | Not started | - |
| 4. Bulk Operations and Provisioning | 0/? | Not started | - |