Files
kawaandClaude Sonnet 4.6 a26608791f chore: complete v1.3 milestone — Backend Expansion
Archives v1.3 milestone (Phase 13: 18 rclone backends), updates PROJECT.md
with all 30 validated requirements, reorganizes ROADMAP.md with all 4 milestones
in collapsed details blocks, adds v1.2 and v1.3 retrospective entries.

Also commits minor CSS token fixes in src/ (text-on-surface-container class
alignment) that were uncommitted from phase 13 execution.

Co-Authored-By: Claude Sonnet 4.6 <noreply@anthropic.com>
2026-04-16 16:54:45 +02:00

2.9 KiB
Raw Permalink Blame History

Roadmap: Ready2Blob

Milestones

  • v1.0 MVP — Phases 14 (shipped 2026-03-27)
  • v1.1 Backlog & Tech Debt — Phases 57 (shipped 2026-03-31)
  • v1.2 UI Polish & Clarity — Phases 812 (shipped 2026-04-01)
  • v1.3 Backend Expansion — Phase 13 (shipped 2026-04-16)

Phases

v1.0 MVP (Phases 14) — SHIPPED 2026-03-27
  • Phase 1: Foundation (4/4 plans) — completed 2026-03-26
  • Phase 2: Generators (4/4 plans) — completed 2026-03-26
  • Phase 3: Wizard UI (5/5 plans) — completed 2026-03-27
  • Phase 4: Review, Download & Security (5/5 plans) — completed 2026-03-27

Full phase details: .planning/milestones/v1.0-ROADMAP.md

v1.1 Backlog & Tech Debt (Phases 57) — SHIPPED 2026-03-31
  • Phase 5: Tech Debt (4/4 plans) — completed 2026-03-30
  • Phase 6: New Backends (4/4 plans) — completed 2026-03-31
  • Phase 7: Validation & UX Polish (3/3 plans) — completed 2026-03-31

Full phase details: .planning/milestones/v1.1-ROADMAP.md

v1.2 UI Polish & Clarity (Phases 812) — SHIPPED 2026-04-01
  • Phase 8: Theme Foundation (2/2 plans) — completed 2026-04-01
  • Phase 9: MD3 Components (5/5 plans) — completed 2026-04-01
  • Phase 10: Content & Clarity (3/3 plans) — completed 2026-04-01
  • Phase 11: Polish & Responsiveness (2/2 plans) — completed 2026-04-01
  • Phase 12: Dark Mode Visibility Fixes (2/2 plans) — completed 2026-04-01

Full phase details: .planning/milestones/v1.3-ROADMAP.md

v1.3 Backend Expansion (Phase 13) — SHIPPED 2026-04-16
  • Phase 13: Add Remaining RClone Remotes (4/4 plans) — completed 2026-04-16

Full phase details: .planning/milestones/v1.3-ROADMAP.md

Progress

Phase Milestone Plans Complete Status Completed
1. Foundation v1.0 4/4 Complete 2026-03-26
2. Generators v1.0 4/4 Complete 2026-03-26
3. Wizard UI v1.0 5/5 Complete 2026-03-27
4. Review, Download & Security v1.0 5/5 Complete 2026-03-27
5. Tech Debt v1.1 4/4 Complete 2026-03-30
6. New Backends v1.1 4/4 Complete 2026-03-31
7. Validation & UX Polish v1.1 3/3 Complete 2026-03-31
8. Theme Foundation v1.2 2/2 Complete 2026-04-01
9. MD3 Components v1.2 5/5 Complete 2026-04-01
10. Content & Clarity v1.2 3/3 Complete 2026-04-01
11. Polish & Responsiveness v1.2 2/2 Complete 2026-04-01
12. Dark Mode Visibility Fixes v1.2 2/2 Complete 2026-04-01
13. Add Remaining RClone Remotes v1.3 4/4 Complete 2026-04-16