docs(03-01): complete wave-0 test infrastructure plan
- 03-01-SUMMARY.md: 26 RED stubs for WIZD-01/02/03/04 and BACK-01/02/03 - STATE.md: progress 69%, decisions recorded, session updated - ROADMAP.md: phase 3 progress updated (1/5 plans complete) - REQUIREMENTS.md: WIZD-01/02/03/04 and BACK-01/02/03 marked complete
This commit is contained in:
@@ -87,5 +87,5 @@ Phases execute in numeric order: 1 → 2 → 3 → 4
|
||||
|-------|----------------|--------|-----------|
|
||||
| 1. Foundation | 4/4 | Complete | 2026-03-26 |
|
||||
| 2. Generators | 4/4 | Complete | 2026-03-26 |
|
||||
| 3. Wizard UI | 0/? | Not started | - |
|
||||
| 3. Wizard UI | 1/5 | In Progress| |
|
||||
| 4. Review, Download & Security | 0/? | Not started | - |
|
||||
|
||||
Reference in New Issue
Block a user