- 4/4 pass (3 in-scope + 1 UX-03 carry-over to Phase 9) - per-phase NYQ-01 coverage complete (7/7 v1.0 phases, 45 rows, 0 roll-forward) - STATE advanced to plan 8 (final 08-08 rollup remaining)
8.6 KiB
gsd_state_version, milestone, milestone_name, current_plan, status, stopped_at, last_updated, last_activity, progress
| gsd_state_version | milestone | milestone_name | current_plan | status | stopped_at | last_updated | last_activity | progress | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.0 | v1.1 | Hardening & Validation | 8 | completed | Completed 08-07-PLAN.md (Phase 7 Nyquist audit) | 2026-04-13T14:20:27.138Z | 2026-04-13 |
|
Project State
Project Reference
See: .planning/PROJECT.md (updated 2026-04-13 after v1.0 milestone)
Core value: Generate a complete, working printer deployment package (script + drivers + icon) in minutes instead of manually scripting each printer setup. Current focus: v1.1 Hardening & Validation — Phase 8 (Nyquist Validation Track)
Current Position
Milestone: v1.1 Hardening & Validation Phase: 08 — Nyquist Validation Track — IN PROGRESS (1/8 plans complete) Current Plan: 8 Total Plans in Phase: 8 Status: Phase 08 active — 08-01 complete, NYQ-01 ticked Decision: 08-01 closed Phase 1 Nyquist audit with 14/14 pass rows; prior real-Intune spike (row 14) resolved PASS by citing Phase 10 RTVAL-01 sign-off rather than fail-fix-v1.1. Last activity: 2026-04-13
Milestone History
- v1.0 — ImpTune MVP (shipped 2026-04-13) — see MILESTONES.md
Accumulated Context
v1.1 Phase Structure
- Phase 8: Nyquist Validation Track (NYQ-01..03) — parallelizable audit track
- Phase 9: UX Tech Debt Closure (UX-01..03) — must land before rollout
- Phase 10: Real-World Runtime Validation (RTVAL-01..05) — must pass before rollout
- Phase 11: Real-World Rollout & Feedback (RWR-01..04) — depends on Phases 9 + 10
Open Concerns (now owned by v1.1 phases)
- Real-world Intune tenant .intunewin acceptance → Phase 10 (RTVAL-01)
pnputil+$PSScriptRootunder SYSTEM → Phase 10 (RTVAL-02..04)- Driver dropdown refresh after upload → Phase 9 (UX-01)
- PRNT-03 Alpine.js port auto-derivation live verification → Phase 9 (UX-02)
- Individual script download links on printer detail page → Phase 9 (UX-03)
- Nyquist-compliant VALIDATION.md across v1.0 phases → Phase 8 (NYQ-01..03)
Decisions
- Phase ordering: RTVAL before RWR (cannot deploy unvalidated runtime); UX before RWR (deployed build must be polished); NYQ parallel to all (pure audit, no code dependency) — placed first so v1.0 validation evidence is fresh before runtime work begins.
- RTVAL grouping: RTVAL-01..05 combined into single Phase 10 because they share setup (same tenant, same test endpoint, same RUNTIME-VALIDATION.md report).
- NYQ as dedicated phase: Kept standalone (not absorbed) because it audits all 7 v1.0 phases and its evidence feeds defect triage into Phases 9/10.
Full decision log in PROJECT.md Key Decisions table. Milestone v1.0 decisions archived in milestones/v1.0-ROADMAP.md.
- [Phase 09-ux-tech-debt-closure]: 09-03: .ps1 routes added as aliases (not renames) to preserve backward compatibility
- [Phase 09-ux-tech-debt-closure]: 09-03: Shared _*_response() helper pattern used for route aliases
- [Phase 09]: Sentinel field (caller=printer_form) for OOB branching: chosen over HX-Target header for clarity and testability
- [Phase 09]: HTMX OOB template includes primary fragment + OOB select sibling in driver_upload_with_oob.html
- [Phase 09-ux-tech-debt-closure]: 09-02: /printers route used for e2e test (full-page with Alpine.js) — no new /printers/new route needed
- [Phase 09-ux-tech-debt-closure]: 09-02: conftest.py adapted — imptune.config uses string paths, init_db() takes no args
- [Phase 10-real-world-runtime-validation]: 10-01: Package under test is Ricoh PCL6 Universal Print (Copieur_2eme.intunewin), ImpTune commit
1c3f458, committed to evidence/ for traceability - [Phase 10-real-world-runtime-validation]: 10-01: Commit SHA locked before runtime testing — all RTVAL results reference this exact build
- [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-01 FAIL — Stop plan 10-02; surface .intunewin structure defect as gap; use /gsd:debug on generator or /gsd:plan-phase 10 --gaps before retesting
- [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-01 PASS on re-test (2026-04-13) — ISSUE-01 resolved by commits
74535ea(HMAC over IV+ciphertext) and7716246(Detection.xml alignment with IntuneWinAppUtil.exe reference format); plan resumed at Task 2 - [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-02 accepted as attestation-only PASS (2026-04-13) — technician verbally confirmed install succeeded on ARES-5CG5220YTM but did NOT provide IntuneManagementExtension.log excerpt or portal screenshot; user explicitly approved "Pass without evidence"; audit trail weakened for this check and flagged in RUNTIME-VALIDATION.md Notes
- [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-03 accepted as attestation-only PASS (2026-04-13) — second consecutive attestation-only check; no rtval-03-detection.png and no rtval-03-detect-manual.txt captured; user was explicitly warned that a second consecutive attestation-only check further weakens the audit trail and still chose to proceed; flagged in RUNTIME-VALIDATION.md Notes as soft PASS requiring re-run with full artifact capture before phase sign-off
- [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-04 accepted as attestation-only PASS (2026-04-13) — third consecutive attestation-only check; no rtval-04-uninstall-log.txt and no rtval-04-uninstall-status.png captured; user was warned a SECOND time about cumulative audit trail damage and still chose to proceed. Together, RTVAL-02/03/04 constitute an attestation-only runtime half for Phase 10: only RTVAL-01 (tenant ingestion) is artifact-backed. Plan 10-03 sign-off must explicitly address whether to re-run RTVAL-02/03/04 with full evidence before closing the phase.
- [Phase 10-real-world-runtime-validation]: 10-02: Plan 10-02 COMPLETE (2026-04-13) — SUMMARY.md created with prominent "Attestation-Only Audit Trail Damage" section for the wave-3 verifier and phase verifier
- [Phase 10-real-world-runtime-validation]: 10-03: Plan 10-03 COMPLETE (2026-04-13) — RUNTIME-VALIDATION.md signed off by Sébastien QUEROL with explicit attestation-gap acknowledgement; REQUIREMENTS.md RTVAL-01..05 ticked (idempotent, already landed in 10-02 commit
206648c); ROADMAP.md Phase 10 flipped to 3/3 Complete 2026-04-13. Phase 10 officially closed. - [Phase 08-nyquist-validation-track]: 08-01: Phase 1 Nyquist Record complete with 14/14 pass rows; row 14 (upload-to-real-Intune spike) resolved PASS citing Phase 10 RTVAL-01 sign-off rather than fail-fix-v1.1
- [Phase 08-nyquist-validation-track]: 08-02: Phase 2 Nyquist Record complete with 6/6 pass rows; POST /drivers/upload 500 historical gap (row 6) closed as pass citing Phase 9 UX-01 fixing commits
d1de839+10ee09a+72c6a98 - [Phase 08-nyquist-validation-track]: 08-03: Phase 3 Nyquist Record complete with 10/10 pass rows; PRNT-03 Alpine.js IP->port historical gap (row 3) closed as pass citing Phase 9 UX-02 Playwright fixing commits
322fc20+37a06da - [Phase 08-nyquist-validation-track]: 08-04: Phase 4 Nyquist Record complete with 5/5 pass rows; SYSTEM-context rows (SCRPT-01/02/03/04/05) cite Phase 10 RTVAL-02/03/04 with explicit attestation-only caveat per STATE.md 2026-04-13 faithfully recorded in Notes
- [Phase 08-nyquist-validation-track]: 08-05: Phase 5 Nyquist Record complete with 5/5 pass rows; PKG-02 row is the ONLY artifact-backed live-tenant runtime row in the 7-phase audit track (cites RTVAL-01 PASS on rubis.fr + fix commits 74535ea/7716246); PKG-04 icon-embedding historical gap closed in place via Phase 6 TestIntunewinIconInclusion
- [Phase 08-nyquist-validation-track]: 08-06: Phase 6 Nyquist Record complete with 1/1 pass row (PKG-04 icon embedding); shortest audit in track reflecting single-criterion gap-closure structure; bidirectional citation loop with 05-VALIDATION row 4; RTVAL-01 cited as supporting transitive runtime evidence
- [Phase 08-nyquist-validation-track]: 08-07: Phase 7 Nyquist Record complete with 4/4 pass (3 in-scope rows anchored to 07-VERIFICATION.md truths since Phase 7 has zero REQUIREMENTS.md IDs, plus 1 UX-03 carry-over row closed via Phase 9 / 09-03); per-phase NYQ-01 coverage complete across all 7 v1.0 phases (45 audit rows total, 0 roll-forward)
Active Blockers
None. BLOCKER-01 resolved 2026-04-13 via commits 74535ea (HMAC over IV+ciphertext) and 7716246 (Detection.xml aligned with IntuneWinAppUtil.exe reference format); RTVAL-01 re-tested PASS on fixed build.
Pending Todos
- Run
/gsd:plan-phase 8to draft plans for Nyquist Validation Track - Schedule real Intune tenant + test endpoint access for Phase 10
- Identify target MSP environment for Phase 11 rollout
Session Continuity
Last session: 2026-04-13T14:20:27.131Z Stopped at: Completed 08-07-PLAN.md (Phase 7 Nyquist audit) Resume file: None