docs(10-03): complete report-signoff plan and close Phase 10

- Mark Phase 10 complete in ROADMAP.md (3/3 plans, 2026-04-13)
- Create 10-03-report-signoff-SUMMARY.md with attestation-gap closure note
- Update STATE.md: plan 10-03 complete, Phase 10 closed, next is phase 8 or 11
- REQUIREMENTS.md RTVAL-01..05 ticks already landed in 10-02 completion commit (idempotent)
This commit is contained in:
2026-04-13 14:32:24 +02:00
parent 5685fd97dc
commit cd2df1e163
3 changed files with 107 additions and 19 deletions
+7 -7
View File
@@ -25,8 +25,8 @@ Full details: [`milestones/v1.0-ROADMAP.md`](milestones/v1.0-ROADMAP.md)
### 🚧 v1.1 Hardening & Validation (Phases 811) ### 🚧 v1.1 Hardening & Validation (Phases 811)
- [ ] **Phase 8: Nyquist Validation Track** — Retro-fit Nyquist-compliant VALIDATION.md across all 7 v1.0 phases with evidence-backed checks - [ ] **Phase 8: Nyquist Validation Track** — Retro-fit Nyquist-compliant VALIDATION.md across all 7 v1.0 phases with evidence-backed checks
- [x] **Phase 9: UX Tech Debt Closure** — Fix the three carried-over UX gaps so the deployed build is the polished one technicians actually use␍ (completed 2026-04-13) - [x] **Phase 9: UX Tech Debt Closure** — Fix the three carried-over UX gaps so the deployed build is the polished one technicians actually use␍ (completed 2026-04-13)
- [ ] **Phase 10: Real-World Runtime Validation** — Validate generated artifacts end-to-end against a live Intune tenant and a real managed endpoint - [x] **Phase 10: Real-World Runtime Validation** — Validate generated artifacts end-to-end against a live Intune tenant and a real managed endpoint (completed 2026-04-13)
- [ ] **Phase 11: Real-World Rollout & Feedback** — Deploy the container to a real MSP environment, push a real package, and capture structured technician feedback - [ ] **Phase 11: Real-World Rollout & Feedback** — Deploy the container to a real MSP environment, push a real package, and capture structured technician feedback
## Phase Details ## Phase Details
@@ -64,10 +64,10 @@ Full details: [`milestones/v1.0-ROADMAP.md`](milestones/v1.0-ROADMAP.md)
3. After install, the Intune detection rule driven by the generated detect script reports "installed" for the endpoint 3. After install, the Intune detection rule driven by the generated detect script reports "installed" for the endpoint
4. A technician triggering uninstall from Intune sees the printer cleanly removed from the endpoint under SYSTEM context 4. A technician triggering uninstall from Intune sees the printer cleanly removed from the endpoint under SYSTEM context
5. A reviewer can open `RUNTIME-VALIDATION.md` and read a signed-off report listing tenant, device, OS build, driver vendor(s), screenshots/logs, and any issues found 5. A reviewer can open `RUNTIME-VALIDATION.md` and read a signed-off report listing tenant, device, OS build, driver vendor(s), screenshots/logs, and any issues found
**Plans**: 3 plans **Plans**: 3 plans
- [ ] 10-01-preflight-package-and-scaffold-PLAN.md — Generate real .intunewin from current commit and scaffold RUNTIME-VALIDATION.md with tenant/device/vendor metadata (RTVAL-05 scaffold) - [ ] 10-01-preflight-package-and-scaffold-PLAN.md — Generate real .intunewin from current commit and scaffold RUNTIME-VALIDATION.md with tenant/device/vendor metadata (RTVAL-05 scaffold)
- [ ] 10-02-live-intune-runtime-validation-PLAN.md — Drive RTVAL-01..04 manual checkpoints against a live Intune tenant + real Windows endpoint, capturing screenshots and device logs as evidence - [ ] 10-02-live-intune-runtime-validation-PLAN.md — Drive RTVAL-01..04 manual checkpoints against a live Intune tenant + real Windows endpoint, capturing screenshots and device logs as evidence
- [ ] 10-03-report-signoff-PLAN.md — Finalize RUNTIME-VALIDATION.md, human sign-off, tick RTVAL-01..05 and mark Phase 10 complete - [ ] 10-03-report-signoff-PLAN.md — Finalize RUNTIME-VALIDATION.md, human sign-off, tick RTVAL-01..05 and mark Phase 10 complete
### Phase 11: Real-World Rollout & Feedback ### Phase 11: Real-World Rollout & Feedback
**Goal**: ImpTune is running in a real MSP environment, has produced a package that actually reached endpoints, and technician feedback has been captured and triaged. **Goal**: ImpTune is running in a real MSP environment, has produced a package that actually reached endpoints, and technician feedback has been captured and triaged.
@@ -93,5 +93,5 @@ Full details: [`milestones/v1.0-ROADMAP.md`](milestones/v1.0-ROADMAP.md)
| 7. Dashboard & Nav Polish | v1.0 | 1/1 | Complete | 2026-04-13 | | 7. Dashboard & Nav Polish | v1.0 | 1/1 | Complete | 2026-04-13 |
| 8. Nyquist Validation Track | v1.1 | 0/? | Not started | — | | 8. Nyquist Validation Track | v1.1 | 0/? | Not started | — |
| 9. UX Tech Debt Closure | 3/3 | Complete | 2026-04-13 | — | | 9. UX Tech Debt Closure | 3/3 | Complete | 2026-04-13 | — |
| 10. Real-World Runtime Validation | 2/3 | In Progress| | — | | 10. Real-World Runtime Validation | v1.1 | 3/3 | Complete | 2026-04-13 |
| 11. Real-World Rollout & Feedback | v1.1 | 0/? | Not started | — | | 11. Real-World Rollout & Feedback | v1.1 | 0/? | Not started | — |
+13 -12
View File
@@ -2,15 +2,15 @@
gsd_state_version: 1.0 gsd_state_version: 1.0
milestone: v1.1 milestone: v1.1
milestone_name: Hardening & Validation milestone_name: Hardening & Validation
status: in-progress — plan 10-02 COMPLETE; all four RTVAL runtime checks recorded (RTVAL-01 artifact-backed PASS, RTVAL-02/03/04 attestation-only PASSes — 3 consecutive, audit trail weakened); ready for plan 10-03 (sign-off) status: in-progress — Phase 10 COMPLETE (signed off 2026-04-13 with explicit attestation-only audit-trail acknowledgement for RTVAL-02/03/04); ready for Phase 8 (Nyquist) or Phase 11 (rollout) planning
stopped_at: 10-02 complete — next is 10-03 sign-off and phase closure stopped_at: Phase 10 complete — next is /gsd:plan-phase 8 or /gsd:plan-phase 11
last_updated: "2026-04-13T00:00:00.000Z" last_updated: "2026-04-13T00:00:00.000Z"
last_activity: 2026-04-13 — Plan 10-02 completed. RTVAL-04 recorded PASS (attestation-only, 3rd consecutive; user warned twice about weakened audit trail and approved). SUMMARY.md created with prominent attestation-only debt section for wave-3 verifier and phase verifier. last_activity: 2026-04-13 — Plan 10-03 completed. RUNTIME-VALIDATION.md signed off by Sébastien QUEROL; REQUIREMENTS.md RTVAL-01..05 ticked; ROADMAP.md Phase 10 marked 3/3 Complete. Phase 10 closed with RTVAL-02/03/04 as accepted attestation-only PASSes.
progress: progress:
total_phases: 4 total_phases: 4
completed_phases: 1 completed_phases: 2
total_plans: 4 total_plans: 4
completed_plans: 4 completed_plans: 5
--- ---
# Project State # Project State
@@ -25,11 +25,11 @@ See: .planning/PROJECT.md (updated 2026-04-13 after v1.0 milestone)
## Current Position ## Current Position
Milestone: v1.1 Hardening & Validation Milestone: v1.1 Hardening & Validation
Phase: 10 — Real-World Runtime Validation Phase: 10 — Real-World Runtime Validation**COMPLETE (2026-04-13)**
Plan: 02 COMPLETE — all 4 tasks recorded (RTVAL-01 artifact-backed PASS; RTVAL-02/03/04 attestation-only PASSes, 3 consecutive). Next plan: 10-03 (sign-off and phase closure). Plan: 03 COMPLETE — RUNTIME-VALIDATION.md signed off by Sébastien QUEROL; REQUIREMENTS.md RTVAL-01..05 ticked; ROADMAP.md Phase 10 marked 3/3 Complete. Next: Phase 8 (Nyquist) or Phase 11 (rollout).
Status: in-progress — plan 10-02 done, plan 10-03 ready to start Status: phase 10 closed — ready for next phase planning
Decision: Plan 10-02 complete with a structurally weakened runtime audit trail. RTVAL-02/03/04 all accepted as attestation-only PASSes per explicit, repeated user approval. User was warned twice (on RTVAL-03 and again on RTVAL-04) that consecutive attestation-only checks damage the audit trail and chose to proceed both times. Plan 10-03 sign-off must explicitly address whether to re-run RTVAL-02/03/04 with full artifact capture before closing the phase. Decision: Phase 10 closed with a structurally weakened runtime audit trail. Only RTVAL-01 is artifact-backed; RTVAL-02/03/04 stand on technician attestation. Reviewer explicitly acknowledged the gap at sign-off and accepted closure on that basis. If a regression, incident, or customer escalation touches SYSTEM-context install/detect/uninstall, RTVAL-02/03/04 must be re-run with full artifact capture before the finding can be trusted.
Last activity: 2026-04-13 — RTVAL-04 PASS (attestation-only, commit 2c912ca); plan 10-02 SUMMARY.md created with prominent attestation-only debt section; plan 10-02 closed Last activity: 2026-04-13 — Plan 10-03 completed; Phase 10 closed; commit 5685fd9 (sign-off) plus 10-03 SUMMARY + ROADMAP/STATE update commit
## Milestone History ## Milestone History
@@ -74,6 +74,7 @@ Full decision log in PROJECT.md Key Decisions table. Milestone v1.0 decisions ar
- [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-03 accepted as attestation-only PASS (2026-04-13) — second consecutive attestation-only check; no rtval-03-detection.png and no rtval-03-detect-manual.txt captured; user was explicitly warned that a second consecutive attestation-only check further weakens the audit trail and still chose to proceed; flagged in RUNTIME-VALIDATION.md Notes as soft PASS requiring re-run with full artifact capture before phase sign-off - [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-03 accepted as attestation-only PASS (2026-04-13) — second consecutive attestation-only check; no rtval-03-detection.png and no rtval-03-detect-manual.txt captured; user was explicitly warned that a second consecutive attestation-only check further weakens the audit trail and still chose to proceed; flagged in RUNTIME-VALIDATION.md Notes as soft PASS requiring re-run with full artifact capture before phase sign-off
- [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-04 accepted as attestation-only PASS (2026-04-13) — **third consecutive attestation-only check**; no rtval-04-uninstall-log.txt and no rtval-04-uninstall-status.png captured; user was warned a SECOND time about cumulative audit trail damage and still chose to proceed. Together, RTVAL-02/03/04 constitute an attestation-only runtime half for Phase 10: only RTVAL-01 (tenant ingestion) is artifact-backed. Plan 10-03 sign-off must explicitly address whether to re-run RTVAL-02/03/04 with full evidence before closing the phase. - [Phase 10-real-world-runtime-validation]: 10-02: RTVAL-04 accepted as attestation-only PASS (2026-04-13) — **third consecutive attestation-only check**; no rtval-04-uninstall-log.txt and no rtval-04-uninstall-status.png captured; user was warned a SECOND time about cumulative audit trail damage and still chose to proceed. Together, RTVAL-02/03/04 constitute an attestation-only runtime half for Phase 10: only RTVAL-01 (tenant ingestion) is artifact-backed. Plan 10-03 sign-off must explicitly address whether to re-run RTVAL-02/03/04 with full evidence before closing the phase.
- [Phase 10-real-world-runtime-validation]: 10-02: Plan 10-02 COMPLETE (2026-04-13) — SUMMARY.md created with prominent "Attestation-Only Audit Trail Damage" section for the wave-3 verifier and phase verifier - [Phase 10-real-world-runtime-validation]: 10-02: Plan 10-02 COMPLETE (2026-04-13) — SUMMARY.md created with prominent "Attestation-Only Audit Trail Damage" section for the wave-3 verifier and phase verifier
- [Phase 10-real-world-runtime-validation]: 10-03: Plan 10-03 COMPLETE (2026-04-13) — RUNTIME-VALIDATION.md signed off by Sébastien QUEROL with explicit attestation-gap acknowledgement; REQUIREMENTS.md RTVAL-01..05 ticked (idempotent, already landed in 10-02 commit 206648c); ROADMAP.md Phase 10 flipped to 3/3 Complete 2026-04-13. Phase 10 officially closed.
### Active Blockers ### Active Blockers
@@ -88,5 +89,5 @@ None. BLOCKER-01 resolved 2026-04-13 via commits 74535ea (HMAC over IV+ciphertex
## Session Continuity ## Session Continuity
Last session: 2026-04-13T00:00:00.000Z Last session: 2026-04-13T00:00:00.000Z
Stopped at: Completed 10-02-live-intune-runtime-validation-PLAN.md — next is plan 10-03 (sign-off and phase closure) Stopped at: Completed 10-03-report-signoff-PLAN.md — Phase 10 closed; next is `/gsd:plan-phase 8` (Nyquist) or `/gsd:plan-phase 11` (rollout)
Resume file: .planning/phases/10-real-world-runtime-validation/10-03-*-PLAN.md (to be drafted or existing) Resume file: — (awaiting next phase kickoff)
@@ -0,0 +1,87 @@
---
phase: 10-real-world-runtime-validation
plan: 03
subsystem: validation/reporting
tags: [runtime-validation, sign-off, phase-closure, rtval]
requirements: [RTVAL-05]
dependency_graph:
requires: [10-01, 10-02]
provides: [signed-off RUNTIME-VALIDATION.md, Phase 10 closure]
affects: [.planning/REQUIREMENTS.md, .planning/ROADMAP.md, .planning/STATE.md]
tech_stack:
added: []
patterns: [human sign-off checkpoint, attestation gap acknowledgement]
key_files:
created:
- .planning/phases/10-real-world-runtime-validation/10-03-report-signoff-SUMMARY.md
modified:
- .planning/phases/10-real-world-runtime-validation/RUNTIME-VALIDATION.md
- .planning/ROADMAP.md
- .planning/REQUIREMENTS.md
decisions:
- Phase 10 closed with RTVAL-02/03/04 as attestation-only PASSes (only RTVAL-01 artifact-backed); reviewer explicitly acknowledged the audit-trail gap at sign-off rather than blocking closure for a re-run.
metrics:
completed_date: 2026-04-13
---
# Phase 10 Plan 03: Report Sign-off Summary
Finalized RUNTIME-VALIDATION.md, obtained human sign-off with explicit attestation-gap acknowledgement, and flipped Phase 10 tracking docs to complete.
## What Was Done
### Task 1 — Finalize RUNTIME-VALIDATION.md report body
Completed in the 10-02 → 10-03 handoff window: all RTVAL-01..04 sections carry concrete PASS/FAIL verdicts, evidence links, and notes; top-level Status was flipped to READY FOR SIGN-OFF by the prior agent.
### Task 2 — Human review and sign-off (checkpoint)
Reviewer Sébastien QUEROL read the report, acknowledged the attestation-only audit-trail gap for RTVAL-02/03/04, and signed off on 2026-04-13:
- Top-level **Status:** flipped to `SIGNED OFF`
- **Signed off by:** Sébastien QUEROL
- **Signed off date:** 2026-04-13
- All three sign-off checkboxes ticked `[x]`
- Reviewer explicitly accepted that only RTVAL-01 is artifact-backed; RTVAL-02/03/04 rest on technician verbal attestation. Compensating controls listed in the report (known device, known tenant, single session, known-good generator) stand in for missing log/screenshot evidence.
Commit: `5685fd9``docs(phase-10): human sign-off on RUNTIME-VALIDATION.md (attestation gap acknowledged)`
### Task 3 — Tick requirements, mark Phase 10 complete
- `.planning/REQUIREMENTS.md` already had RTVAL-01..05 ticked `[x]` and the Traceability table showing `Complete` for each (landed in the 10-02 completion commit `206648c`). Idempotent confirmation only — no edits needed.
- `.planning/ROADMAP.md`:
- Phase 10 entry flipped from `[ ]` to `[x]` with `(completed 2026-04-13)` appended.
- Progress table row for Phase 10 set to `v1.1 | 3/3 | Complete | 2026-04-13`.
## Verification
- `grep "^\*\*Status:\*\* SIGNED OFF" RUNTIME-VALIDATION.md` → hit
- `grep "Signed off by:\*\* Sébastien QUEROL" RUNTIME-VALIDATION.md` → hit
- Zero `Status: PENDING` lines in the report
- `grep "\[x\] \*\*RTVAL-05\*\*" REQUIREMENTS.md` → hit
- `grep "\[x\] \*\*Phase 10" ROADMAP.md` → hit
- ROADMAP.md Progress row for Phase 10 shows `3/3 | Complete | 2026-04-13`
All verification checks from the plan pass.
## Deviations from Plan
None. Task 3 REQUIREMENTS.md edits were already present from plan 10-02's completion commit, making that step a no-op confirmation rather than a mutation. No deviation rules (1-4) triggered.
## Phase 10 Closure Note — Attestation-Only Audit Trail
Phase 10 closes with a structurally weakened runtime audit trail that downstream consumers must be aware of:
- **RTVAL-01** (tenant ingestion): PASS, artifact-backed (screenshots + exact .intunewin package committed under `evidence/`), re-tested on the fixed build after ISSUE-01 was resolved (commits `74535ea` + `7716246`).
- **RTVAL-02** (install under SYSTEM): PASS, **attestation-only** — no `IntuneManagementExtension.log` excerpt, no portal screenshot.
- **RTVAL-03** (detection rule): PASS, **attestation-only, 2nd consecutive** — no portal screenshot, no manual detect transcript.
- **RTVAL-04** (uninstall under SYSTEM): PASS, **attestation-only, 3rd consecutive** — no uninstall log, no portal screenshot.
RTVAL-02/03/04 together form an attestation-only runtime half for the phase. The user was warned twice during plan 10-02 (on RTVAL-03 and again on RTVAL-04) that consecutive attestation-only checks damage the audit trail, and chose to proceed both times. At sign-off the user again explicitly acknowledged the gap and accepted Phase 10 closure on that basis.
**Implication for future work:** If a regression, incident, or customer escalation touches SYSTEM-context install, detection, or uninstall, RTVAL-02/03/04 must be treated as soft PASSes — the "it worked once" claim for this build cannot be independently re-derived from evidence files and must be re-validated with full artifact capture. Phase 11 rollout proceeds at the reviewer's risk.
## Self-Check: PASSED
- FOUND: `.planning/phases/10-real-world-runtime-validation/RUNTIME-VALIDATION.md` (SIGNED OFF)
- FOUND: `.planning/phases/10-real-world-runtime-validation/10-03-report-signoff-SUMMARY.md`
- FOUND: REQUIREMENTS.md RTVAL-01..05 ticked + Traceability Complete
- FOUND: ROADMAP.md Phase 10 ticked with 3/3 Complete 2026-04-13
- FOUND commit: `5685fd9` (Task 2 sign-off)