docs(11-01): complete UIE-02 plan — Add Printer page separation
- Create 11-01-SUMMARY.md with full execution record - Update STATE.md: advance plan to 3, add decisions, update session - Update ROADMAP.md: phase 11 progress to 1/4 summaries (In Progress)
This commit is contained in:
+13
-11
@@ -2,16 +2,16 @@
|
||||
gsd_state_version: 1.0
|
||||
milestone: v1.1
|
||||
milestone_name: Hardening & Validation
|
||||
current_plan: 2
|
||||
current_plan: 3
|
||||
status: completed
|
||||
stopped_at: Phase 11 context gathered
|
||||
last_updated: "2026-04-15T08:33:07.274Z"
|
||||
last_activity: 2026-04-13
|
||||
stopped_at: Completed 11-ui-enhancements/11-01-PLAN.md
|
||||
last_updated: "2026-04-15T09:04:38.757Z"
|
||||
last_activity: 2026-04-15
|
||||
progress:
|
||||
total_phases: 4
|
||||
completed_phases: 3
|
||||
total_plans: 14
|
||||
completed_plans: 14
|
||||
total_plans: 18
|
||||
completed_plans: 15
|
||||
---
|
||||
|
||||
# Project State
|
||||
@@ -27,11 +27,11 @@ See: .planning/PROJECT.md (updated 2026-04-13 after v1.0 milestone)
|
||||
|
||||
Milestone: v1.1 Hardening & Validation
|
||||
Phase: 09 — UX Tech Debt Closure — ACTIVE (1/3 plans complete)
|
||||
Current Plan: 2
|
||||
Current Plan: 3
|
||||
Total Plans in Phase: 3
|
||||
Status: Phase 09 active — 09-01 complete (UX-01: driver upload 500 fixed + HTMX OOB refresh wired)
|
||||
Decision: 09-01 delivered caller-aware upload handler, driver_upload_with_oob.html template, inline upload form in printer_form.html, and 5 new integration tests (500 regression x2, OOB contract x3).
|
||||
Last activity: 2026-04-13
|
||||
Last activity: 2026-04-15
|
||||
|
||||
## Milestone History
|
||||
|
||||
@@ -87,6 +87,8 @@ Full decision log in PROJECT.md Key Decisions table. Milestone v1.0 decisions ar
|
||||
- [Phase 08-nyquist-validation-track]: 08-08: v1.0-VALIDATION-INDEX.md signed off 2026-04-13 by Sébastien QUEROL; 45/45 pass across 7 phases, 0 fail-fix-v1.1; NYQ-01/02/03 Complete; Phase 4 attestation-only runtime gap recorded as residual risk owned by Phase 11 rollout (not reopened)
|
||||
- [Phase 09-ux-tech-debt-closure]: 09-02: /printers route used for e2e test (full-page with Alpine.js) — no new /printers/new route needed
|
||||
- [Phase 09-ux-tech-debt-closure]: 09-02: conftest.py adapted — imptune.config uses string paths, init_db() takes no args
|
||||
- [Phase 11-ui-enhancements]: 11-01: Plain HTML form in printers_new.html (Option A) — no hx-post, uses action=/printers method=post so browser follows 303 redirect naturally
|
||||
- [Phase 11-ui-enhancements]: 11-01: driver_data context kept in GET /printers handler for future Plan 02 edit modal
|
||||
|
||||
### Active Blockers
|
||||
|
||||
@@ -100,6 +102,6 @@ None. BLOCKER-01 resolved 2026-04-13 via commits 74535ea (HMAC over IV+ciphertex
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-04-15T08:33:07.270Z
|
||||
Stopped at: Phase 11 context gathered
|
||||
Resume file: .planning/phases/11-ui-enhancements/11-CONTEXT.md
|
||||
Last session: 2026-04-15T09:04:38.754Z
|
||||
Stopped at: Completed 11-ui-enhancements/11-01-PLAN.md
|
||||
Resume file: None
|
||||
|
||||