docs(09-02): complete playwright-port-autofill plan

- STATE.md: advance to plan 2, record UX-02 closure decisions
- ROADMAP.md: Phase 9 now 3/3 summaries (Complete)
- Task commits already in history: 4e9bd9b (scaffolding) + 322fc20 (test)
- 1 Playwright test green: test_port_autofill[chromium] PASSED in 5.49s
- 113 unit tests unaffected

Co-Authored-By: Claude Sonnet 4.6 <noreply@anthropic.com>
This commit is contained in:
2026-04-13 17:46:38 +02:00
co-authored by Claude Sonnet 4.6
parent fb7555e6b5
commit 70454c8e14
2 changed files with 11 additions and 10 deletions
+10 -9
View File
@@ -2,17 +2,16 @@
gsd_state_version: 1.0
milestone: v1.1
milestone_name: Hardening & Validation
current_phase: 09-ux-tech-debt-closure
current_plan: 1
status: active
stopped_at: Completed 09-01-driver-upload-fix-and-inline-oob-PLAN.md
last_updated: "2026-04-13T15:42:17.780Z"
current_plan: 2
status: completed
stopped_at: Completed 09-02-playwright-port-autofill-PLAN.md
last_updated: "2026-04-13T15:46:11.154Z"
last_activity: 2026-04-13
progress:
total_phases: 4
completed_phases: 3
total_plans: 17
completed_plans: 15
completed_plans: 14
---
# Project State
@@ -28,7 +27,7 @@ See: .planning/PROJECT.md (updated 2026-04-13 after v1.0 milestone)
Milestone: v1.1 Hardening & Validation
Phase: 09 — UX Tech Debt Closure — ACTIVE (1/3 plans complete)
Current Plan: 1
Current Plan: 2
Total Plans in Phase: 3
Status: Phase 09 active — 09-01 complete (UX-01: driver upload 500 fixed + HTMX OOB refresh wired)
Decision: 09-01 delivered caller-aware upload handler, driver_upload_with_oob.html template, inline upload form in printer_form.html, and 5 new integration tests (500 regression x2, OOB contract x3).
@@ -86,6 +85,8 @@ Full decision log in PROJECT.md Key Decisions table. Milestone v1.0 decisions ar
- [Phase 08-nyquist-validation-track]: 08-06: Phase 6 Nyquist Record complete with 1/1 pass row (PKG-04 icon embedding); shortest audit in track reflecting single-criterion gap-closure structure; bidirectional citation loop with 05-VALIDATION row 4; RTVAL-01 cited as supporting transitive runtime evidence
- [Phase 08-nyquist-validation-track]: 08-07: Phase 7 Nyquist Record complete with 4/4 pass (3 in-scope rows anchored to 07-VERIFICATION.md truths since Phase 7 has zero REQUIREMENTS.md IDs, plus 1 UX-03 carry-over row closed via Phase 9 / 09-03); per-phase NYQ-01 coverage complete across all 7 v1.0 phases (45 audit rows total, 0 roll-forward)
- [Phase 08-nyquist-validation-track]: 08-08: v1.0-VALIDATION-INDEX.md signed off 2026-04-13 by Sébastien QUEROL; 45/45 pass across 7 phases, 0 fail-fix-v1.1; NYQ-01/02/03 Complete; Phase 4 attestation-only runtime gap recorded as residual risk owned by Phase 11 rollout (not reopened)
- [Phase 09-ux-tech-debt-closure]: 09-02: /printers route used for e2e test (full-page with Alpine.js) — no new /printers/new route needed
- [Phase 09-ux-tech-debt-closure]: 09-02: conftest.py adapted — imptune.config uses string paths, init_db() takes no args
### Active Blockers
@@ -99,6 +100,6 @@ None. BLOCKER-01 resolved 2026-04-13 via commits 74535ea (HMAC over IV+ciphertex
## Session Continuity
Last session: 2026-04-13T15:41:00Z
Stopped at: Completed 09-01-driver-upload-fix-and-inline-oob-PLAN.md
Last session: 2026-04-13T15:46:11.145Z
Stopped at: Completed 09-02-playwright-port-autofill-PLAN.md
Resume file: None